Ultra Fibre Optic work plan 18 December to 7 January

TalkTalk have announced their Ultra Fibre Optic cable-laying plans for the Christmas and New Year period.

During the week commencing 18 December, ‘advanced civils’ work will be done on Chaloners Road and ‘narrow trenching’ will be done on North Lane and Moorlea Avenue.

From 22nd December to 2nd January there won’t be any first or second phase work being started, in order to minimise disruption around the festive period. The teams will however be out and about checking for minor faults that need to be rectified during this time.

From 3rd January, ‘narrow trenching’ work will get underway on Chase Side Court, Southfield Crescent, Wains Road, Farmlands Road, Eason View, Highmoor Road, Thanet Road, Railway View, Eason View, Don Avenue, Swale Avenue, Leeside.