Ultra Fibre Optic – work plan for w/c 13 November

The work to install Ultra Fibre Optic cable across west York continues, with the following streets due to be visited during the week commencing 13 November for ‘advanced civils’ work:

  • Wordsworth Crescent
  • Acorn Way
  • Allendale
  • Sandmartin Court
  • Foxton
  • Chantry Close
  • Deepdale
  • Carrfield
  • Summerfield Road
  • Ryecroft Avenue
  • Lowick
  • Grassholme
  • Heron Avenue
  • Sherringham Drive

In addition to the streets listed above, ‘narrow trenching’ work will be undertaken on Leeside, Swale Avenue, Don Avenue and Eason View.

UFO works planned for w/c 13 November

Ultra Fibre Optic – work plan for w/c 30 October

The work to install Ultra Fibre Optic cable across west York continues, with the following streets due to be visited during the week commencing 30 October:

Chase Side Court
Eason View
Bannisdale
Lindale
Lowick
Miterdale
Skiddaw
Stonethwaite
Troutbeck
Crummock
Nairn Close
Quaker Green
Annan Close
Eden Close
Grassholme
Orrin Close
Spey Bank
Moor Lane

In addition, ‘narrow trenching’ work will start on St James Croft, Orchard Close and The Pastures.

Ultra Fibre Optic – work plan for w/c 23 October

The work to install Ultra Fibre Optic cable across west York continues, with the following streets due to be visited during the week commencing 23 October:

Chaloners Road

Acorn Way

Ullswater

Arundel Grove

Overdale Close

Bramble Dene

Glaisdale

Chapmans Court

Windermere

Trent Way

Glenridding

Silverdale Court


In addition, work is underway on Alness Drive so that the cable laying is completed before the council starts work on resurfacing footpaths.

 

Alness Drive footpath resurfacing work announced

We are pleased to report that work will shortly get underway to resurface footpaths on Alness Drive and on Deveron Way. The sections of path to be resurfaced are marked on the map below. The area of block paving on Deveron Way is to be replaced with tarmac.

Letters are being delivered to residents, with a request that any vegetation overhanging the footpath is cut back. The work is due to get underway from 30 October and is expected to take eight weeks.


Ashbourne Way/Acomb Wood Close footpaths to be resurfaced

The City of York Council will start work week commencing 18th September 2017 to reconstruct some of the footways shown on the plan below.  This scheme is programmed to take 2 weeks, weather permitting.

The work consists of excavating the current tarmac surfacing, laying two new layers of tarmac and replacing road kerbs within vehicle crossings.

Residents are being offered a discount on any new driveway requirements that they may wish to commission while plant is in the area.

Hob Moor footpath gets much-needed repair

The large hole which appeared in the footpath on Hob Moor near the railway underpass has been repaired after we reported it for attention.

This section of footpath had started to crumble away, and it seems to have been related to utilities work that was carried out some time ago.

Repair work underway

Before – the footpath was in dire need of attention

Changes planned for Tadcaster Road/St Helen’s Road junction

As part of a plan to upgrade the traffic signals at the St Helens Road junction a new Puffin pedestrian crossing facility is to be provided on the north side of the junction.

Full details are contained in this report

The report says,

“The replacement of the existing island has been proposed because the island is too narrow. It falls below minimum design guidance in terms of its overall width and the distance of its guard rails from the carriageway.

The substandard width results in difficulty for pedestrians in using the facility, especially those with prams and wheelchairs.

The substandard distance of the guardrail to the carriageway has resulted in vehicle strikes which in turn creates a maintenance liability.

The addition of a third pedestrian crossing on the north arm of the junction constitutes as ‘easy win’, in that it provides a desirable pedestrian facility without any significant detriment to the functioning of the junction.

There is no significant change to vehicular delays, queues, Practical Reserve Capacity or congestion.

Introduction of an additional pedestrian crossing on the north arm of the junction is a significant improvement for pedestrians as it serves a desire line accessing the inbound bus stop and Cross Keys public house.

Changes to traffic signals and junction layouts at George Hudson Street and East Parade in Heworth are also being considered

The same meeting will also consider a report following the presentation of a petition asking for carriageway repair works on The Horseshoe

 

 

Big programme of highway resurfacing works announced for Dringhouses and Woodthorpe area

The York Council has announced which roads and footpaths will be resurfaced this year. The programme is the biggest for several years with, in total, £8,091,500 is due to be invested.

This represents an increase of 27% over the previous years budget

Around 100 individual roads are listed for resurfacing.

In the Dringhouses area, the programme includes £1/4 million for work on the following roads and footpaths

Bracken Road Carriageway Dringhouses £81,000
Middlethorpe Grove Carriageway Dringhouses £137,000
Little Hob Moor Cycle path Dringhouses £1,750
Acomb Wood Close Footpath Dringhouses £4,000
Alness Drive Footpath Dringhouses £27,000
Ashbourne Way Footpath Dringhouses £5,000
Deveron Way Footpath Dringhouses £14,000
North Lane Footpath Dringhouses £7,000
Old Moor Lane Footpath Dringhouses £7,120

The full list of streets which will receive attention can be viewed by clicking here